After
years of planning, anticipation, design and development,
the first phase of Cahersiveen Marina and Water Activity
Centre is now weeks away from receiving its first yacht.
To
achieve the required water depth in the Marina of 2.5m
some further localised dredging remains to be completed.
The local contractor, John Quirke Construction, has
appointed a specialist company to carry out this work.
It is expected that they will be on site in the Marina
until the end of May.
Walcon Marine will then return to site to anchor the
pontoons and fix the berthing fingers.
The
electrical installation company Rolec are the final
contractors to come on site to complete the services
work.
The
construction team are confident that the Marina will
be fully operational by mid-June, by which time it will
have been constructed within its €3.8million budget.
ACARD
looks forward to meeting you all at the official opening,
in the very near future.
Denis
OSullivan
Chairperson, ACARD Limited
|