|
|
|
|
|
ISSUE
6- SPECIAL EDITION ACARD Limited - Cahersiveen Community
Development
October 2002
|
|
Introduction
The development of a new concept in any area can be
difficult, but aligning this to a challenging engineering
project makes for quite a challenge. Add to this recipe
the involvement of a local, voluntary community organisation
determined to improve the viability of a remote rural
area, and you have the makings of a truly groundbreaking
enterprise. The development of Cahersiveen Marina and
Water Activity Centre is a unique partnership of community,
local authority and state commitment, all driven forward
by a private company specialising in such cross-disciplinary
projects.
Marian Flannery, Principal Partner, Development Solutions
Consultancy, comments that as a result of interest being
shown by a local development group in recent years,
an opportunity arose to assemble a unique public-community
development partnership to provide a leisure marina
in remote Cahersiveen, Co. Kerry. "105 berths have
been provided in the first phase of the development,
which will have a capability of generating over €2million
per annum in the local economy. Phase Two will provide
for a purpose built Clubhouse and on-shore facilities."
Following strong recommendation, Niall Fitzsimons and
Company were retained
as Consulting Structural Engineers for the development.
The development was designed as a cost-effective rock-armour
marine wall to the marina basin, with a floating breakwater
and pontoons.
Revised Design
The development started life as a more traditional sheet-piled
basin to be constructed in an area of neglected river
frontage, which had previously formed part of the town
tip, in days before marine pollution was taken into
consideration. However, as a result of post tender discussions
with the successful contractor, the design was revised
to incorporate rock-armour using locally sourced materials,
together with a novel floating breakwater solution.
This method of construction significantly reduced the
capital cost the project, although did result in the
basin size being reduced to accommodated the 45o batter
of the rock-armour.
|
|
The
need to deliver the project on a very tight budget,
driven by financial resources made available through
the Department of the Marine, matched by local contribution,
lead to a close working relationship between Project
Managers, Development Solutions Consultancy, the Consulting
Structural Engineers, the Main Contractor, John Quirke
and Sons, Kerry County Council, and the Department,
which continued for the duration of the works. As the
formation of the basin effectively comprised the critical
path for the entire project, verification of the reduced
level was paramount.
Niall Fitzsimons explains, "The construction technique
was designed to be simple, involving little expensive
equipment. The design team adopted a procedure of excavating
in the dry behind bund walls, permitting the use of
land-based hydraulic machines. Upon completion of the
excavation, the pumps were withdrawn and the bund wall
was carefully removed, allowing the basin to fill".

Oliver Ring, Senior Executive Engineer, Kerry County
Council notes that "as with most marine works,
this project proved exciting and demanding and the result
is a credit to all who worked on it."
Martin Nolan, County Manager, Kerry County Council adds,
"the main challenge with the project was to assemble
a competent technical team to bring the development
home in time and on budget. The introduction of Development
Solutions Consultancy was pivotal in achieving this
objective."
Partnership
Speaking about the €4million development, John
Quirke of John Quirke and Sons congratulated ACARD Limited,
the voluntary local development group on the finished
development, identifying the partnership between client
and company as a critical element in the project's success.
It was an intensive project according to John. "We
needed to bring this marine construction in on a very
tight budget, and this defined our delivery approach.
Whilst of relatively small scale, this project epitomises
the quality of work that can be achieved by partnership
action."
Capital Investment
|
|
For
ACARD Limited too, the Cahersiveen Marina and Water
Activity Centre is part of a wider picture, says Chairperson
Denis O'Sullivan. "Phase One opened in August,
to coincide with the important Cahersiveen Celtic Music
Festival. Work on Phase Two will be commencing within
12 months, and forms part of our dynamic five-year public-private
development plan for the Valentia River frontage,"
he says.
Funding
for Phase One provided a significant challenge to ACARD
Limited - voluntary community groups rarely get involved
in such capital intensive developments. The need to
generate significant levels of local contribution was
achieved using the ingenuity of Development Solutions
Consultancy, who were given the task of pre-leasing
thirty berths to generate matching finance. This target
was achieved by the spring of 2002.
Cahersiveen Marina and Water Activity Centre represents
a unique marine project taking the meaning of partnership
projects to a new level. The project has overcome scepticism
and technical problems to deliver a very cost-effective
element of local infrastructure through the engagement
of the local community, local government, and the state
working in harmony.
Completion
At the launch of the project, the role of Development
Solutions as the major co-ordinating and driving force
behind the development was noted by all those involved.
Minister John 'O Donoghue, T.D. complemented Project
Manager, Marian Flannery of the company, for her enormous
energy and drive. Her unique knowledge and background
in dealing with local government and state agencies
made his political task in delivering funding for the
project more achievable. Kerry County Manager, Martin
Nolan, commented that Ms. Flannery's attention to detail
in producing economically sustainable and realistic
proposals were a major contributory factor to the securing
of initial funding, while her astute liaison on a political
level, both locally and nationally ensured ongoing confidence
in the project.
Finally, Mr. George O'Doherty of the Department of the
Marine and Natural Resources, said the fact that the
Cahersiveen project came in ahead of schedule, as against
many similar private projects, was a tribute to all
those involved. In particular he pointed to the management
skills of Development Solutions, who delivered such
a new approach, giving encouragement to any community
or private group who want to become involved in such
a venture.
Previous
Issues:
Issue
5, Issue 4
|
|

 |
|
|
|
|